PMP認(rèn)證考試練習(xí)題及參考答案(二)
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
來源:考試大網(wǎng)1. the highest degrees of project risk and uncertainty are associated with the following phase of the project:
a. conceptual
b. execution
c. cut-over來源:www.examda.com
d. post project evaluation
e. a and d only
ans: a
2. the most common types of schedules are gantt charts, milestone charts, line of balance, and:
a. networks.
b. time phased events.
c. calendar integrated activities.
d. a and c only.
e. b and c only.
ans: a
3. which of the following is often overlooked in achieving effective communication?
a. speaking clearly
b. listening
c. interpreting
d. maintaining eye contact
e. manipulating the conversation
ans: b
4. which type of contract requires that the buyer keep the tightest labor/material cost control?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee考試大論壇
d. firm fixed price
e. firm fixed price plus incentive
ans: b
5. a task-oriented family tree of activities is a:
a. detailed plan.
b. linear responsibility chart.
c. work breakdown structure.
d. cost account coding system.
e. work package description.
ans: c
6. adding 5 people to a 4 person team increases the communication channels by a factor of:
a. 2 times
b. 3 times
c. 4 times來源:考試大
d. 5 times
e. 6 times
ans: e
7. cost management includes:
a. cost estimating/forecasting.
b. cost budgeting/cost control.
c. cost applications.
d. all of the above.
e. a and b only.
ans: d
8. participative management:
a. involves the solicitation of information from all team members.
b. assumes that members avoid work and responsibility.
c. suggests the sharing of power and decision making.
d. employs a theory x style of leadership.
e. a and c
ans: e
9. the auditing function that provides feedback about the quality of output is referred to as:
a. quality control.
b. quality planning.
c. quality assurance.
d. quality improvement
e. all of the above.
ans: c
10. the lowest dollar amount 'at stake' is associated with the following phase of the project:
a. conceptual
b. execution來源:www.examda.com
c. cut-over
d. post project evaluation
e. a and d only
ans: a
11. the major disadvantage of a bar chart is:
a. lack of time-phasing.
b. cannot be related to calendar dates.
c. does not show activity interrelationships.
d. cannot be related to manpower planning.
e. cannot be related to cost estimates.
ans: c
12. which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee
d. firm fixed pricewww.Examda.CoM
e. firm fixed price plus incentive
ans: e
本站推薦
- 1PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項(xiàng)目進(jìn)度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項(xiàng)目管理,項(xiàng)目進(jìn)度管理的疑問終結(jié)者,您還在等什么?
- 4項(xiàng)目進(jìn)度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目效率翻倍?答案就在這里!
- 6項(xiàng)目進(jìn)度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項(xiàng)目管理不再迷茫,PMP進(jìn)度系統(tǒng):您的疑問我來答
- 8PMP在手,項(xiàng)目進(jìn)度管理難題還用問嗎?輕松搞定
- 9還在為項(xiàng)目進(jìn)度頭疼?PMP管理系統(tǒng)幫您一問解千愁!