PMP認(rèn)證考試試題精選(6.1)
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
1. The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called:
a. parametric estimation.
b. scope definition.
c. feasibility analysis.
d. benefit-cost analysis.
2. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called:
a. strategic planning.
b. alternative objectives inventory.
c. management by objectives.
d. contingency planning.
3. A fundamental tenet of modern quality management holds that quality is most likely to be achieved by:
a. planning it into the project.
b. developing final inspections for quality.
c. striving to do the best job possible.
d. conducting quality circle activities.
4. The time-phased budget that will be used to measure and monitor cost performance in he project is called the:
a. work breakdown structure.
b. project schedule.
c. cost baseline.
d. cost budget.
5. At XYZ Inc., the hourly wage for semi-skilled workers is .00. The annual audit shows that fringe benefits cost 30% of basic wages, and that overhead costs are 60% of wages plus fringe benefits. What is the “l(fā)oaded” hourly wage for a semi-skilled worker at XYZ Inc.?
a. .40.
b. .60.
c. .12.
d. .33.
6. When there is uncertainty associated with one or more aspects of the project, one of the first steps to take is to:
a. revise project plan.
b. conduct a risk-benefit analysis.
c. conduct a needs analysis.
d. increase the estimated cost.
7. A narrative description of products or services to be supplied under contract is called:
a. the project plan.
b. a statement of work.
c. an exception report.
d. Pareto analysis.
8. An example of scope verification is:
a. reviewing the performance of an installed software module.
b. managing changes to the project schedule.
c. decomposing the WBS to a work package level.
d. performing a benefit/cost analysis to determine if the project should proceed.
9. All of the following are examples of a source of scope change except:
a. a variation in government regulations.
b. failure to include a required feature in the design of a telecommunication system.
c. discovering a need to engage in bottom-up cost estimating.
d. introducing technology that was not available when scope was originally defined.
本站推薦
- 1PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項(xiàng)目進(jìn)度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項(xiàng)目管理,項(xiàng)目進(jìn)度管理的疑問終結(jié)者,您還在等什么?
- 4項(xiàng)目進(jìn)度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目效率翻倍?答案就在這里!
- 6項(xiàng)目進(jìn)度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項(xiàng)目管理不再迷茫,PMP進(jìn)度系統(tǒng):您的疑問我來答
- 8PMP在手,項(xiàng)目進(jìn)度管理難題還用問嗎?輕松搞定
- 9還在為項(xiàng)目進(jìn)度頭疼?PMP管理系統(tǒng)幫您一問解千愁!