PMP認(rèn)證考試練習(xí)題及參考答案(二十一)
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
1. which of the following is referred to as payback period:
a. the number of periods required to recover the initial investment
b. the rate of return on the investment
c. the number of periods required to bring project cost back to the original budget, based on current performance
d. loan payment schedule
e. none of the above
ans: a
2. which one of the following is not an acquisition method?
a. advertising
b. invitation
c. negotiation
d. purchase考試大論壇
e. all are acquisition methods
ans: a
3. at least _____of the cost of quality are the direct responsibility of management.
a. 0.25
b. 0.85
c. 0.5
d. 1
e. 0.33
ans: b
4. fast tracking means to:
a. speed up a project through parallel tasks.
b. swap one task for another.
c. reduce the number of tasks if possible.
d. b and c.
e. none of the above.
ans: a來源:考試大網(wǎng)
5. formal written correspondence is mandated in which of the following situations:
a. product undergoes casual in-house testing
b. client requests additional work not covered under contract
c. project manager calls a meeting
d. b and c only
e. none of the above
ans: b
6. the delphi method is _____ .
a. used to derive a consensus arriving at a convergent solution
b. useful in determining probability relating to future events.
c. used with questionnaires based on established scenarios.
d. continued as an iterative process until a solution is reached.
e. all of the above.
ans: e
7. the positive value of conflict is underestimated. properly managed, conflict is a valuable tool, particularly when
a. a diversion is needed
b. conflictive situations are in their early stages and emotional involvement is low
c. conflictive situations are in their late stages and emotional involvement is high
d. conflict may cause a loss of status or position power
e.
ans: b
8. under the terms of 2/10 net 30, the buyer may:來源:考試大
a. deduct 10% of the invoice amount for payment within 30 days
b. deduct 2% of the invoice for payment within 10 days
c. incurs a penalty on 10% for payments more than 30 days late
d. settle the invoice with 2 equal payments; one within 10 days and the other within 30 days
e. none of the above
ans: b
9. which of the following can result in misinterpretation of the statement of work?
a. using imprecise language (i.e. nearly, approximately)
b. mixing tasks, specifications, special instructions and approvals
c. no pattern, structure or chronological order
d. wide variation in the size of tasks or details of work
e. all of the above
ans: e
10. amount at stake is the _____ .
a. function of planned time/real time project costs.
b. risk identified in successful project completions.
c. (standard project deviation + expected costs)/6
d. cost of investment loss + least cost to restore status quo.
e. inherent risk at conception altered by standard project deviations.來源:考試大網(wǎng)
ans: d
11. in communications management, to assimilate through the mind or senses (as in new ideas) is the process of
a. understanding
b. communicating
c. receiving
d. decoding
e. comprehending
ans: c
12. in general, the best long-lasting approach to settling project conflict is the _____ approach .
a. problem solving
b. compromise
c. withdrawal
d. smoothing
e. forcing
ans: a
本站推薦
- 1PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項(xiàng)目進(jìn)度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項(xiàng)目管理,項(xiàng)目進(jìn)度管理的疑問終結(jié)者,您還在等什么?
- 4項(xiàng)目進(jìn)度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目效率翻倍?答案就在這里!
- 6項(xiàng)目進(jìn)度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項(xiàng)目管理不再迷茫,PMP進(jìn)度系統(tǒng):您的疑問我來答
- 8PMP在手,項(xiàng)目進(jìn)度管理難題還用問嗎?輕松搞定
- 9還在為項(xiàng)目進(jìn)度頭疼?PMP管理系統(tǒng)幫您一問解千愁!