PMP認(rèn)證考試練習(xí)題及參考答案(六)
1. smoothing out resource requirements from period to period is called resource _____.
a. allocation.
b. partitioning
c. leveling.來源:考試大
d. quantification
e. none of above.
ans: c
2. the most precise or accurate estimate for determining project costs is the _____ estimate.
a. definitive.
b. analogy
c. budget
d. modified standards.
e. rule of thumb.
ans: a
3. when subordinates know pertinent information that is not known by the project manager, the result is:
a. blindspot
b. facade
c. region of influence
d. communication power base
e. none of the above
ans: a
4. which of the following scheduling methods uses more of the risk management concepts:
a. adm
b. pdm
c. cpm
d. pert來源:www.examda.com
e. gantt
ans: d
5. which of the following terms refers to the situation where the work is being used for the purpose intended and so certified:
a. beneficial completion
b. substantial completion
c. project completion
d. contract closeout
e. final completion
ans: b
6. a _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
a. parametric
b. definitive.
c. budget
d. bottom up.
e. top down.
ans: c
7. assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.
a. allocation.
b. partitioning
c. leveling
d. quantification.
e. none of above.
ans: a
8. for communication to occur, there must be:
a. two or more people involved
b. the transmittal of information
c. a communication process
d. all of the above
e. b and c only來源:考試大網(wǎng)
ans: d
9. the ability to get an individual or group to perform a given task is best described as:
a. authority
b. power
c. influence
d. leadership
e. coerciveness
ans: b
10. the comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:
a. post project evaluation
b. post contract evaluation
c. post mortem
d. procurement performance evaluation
e. contractor's performance evaluation
ans: e
11. the financial closeout of a project dictates that:
a. all project funds have been spent.
b. no charge numbers have been overrun.來源:考試大
c. no follow-on work from this client is possible.
d. no further charges can be made against the project.
e. all of the above.
ans: d
12. two sources of variation in the length of hex bolts exist. production variation and measurement error. the qc manager knows that the
standard deviation from these sources is 0.24" and 0.43" , respectively. what is the total standard deviation.
a. .10 inch.
b. .19 inch.
c. .34 inch.
d. .49 inch.
e. .67 inch.
ans: d
本站推薦
- 1PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目一馬當(dāng)先?答案當(dāng)然是肯定的!
- 2項(xiàng)目進(jìn)度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項(xiàng)目管理,項(xiàng)目進(jìn)度管理的疑問終結(jié)者,您還在等什么?
- 4項(xiàng)目進(jìn)度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目效率翻倍?答案就在這里!
- 6項(xiàng)目進(jìn)度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項(xiàng)目管理不再迷茫,PMP進(jìn)度系統(tǒng):您的疑問我來答
- 8PMP在手,項(xiàng)目進(jìn)度管理難題還用問嗎?輕松搞定
- 9還在為項(xiàng)目進(jìn)度頭疼?PMP管理系統(tǒng)幫您一問解千愁!