2010年P(guān)MP美國項目管理考試習(xí)題及答案27
QUEST A contract originated bilaterally may be developed by _____ .
A quotation request from suppliers
B proposal request
C bid invitation release
D B and C
E All of the above.
參考答案:E
QUEST A legally binding document offered unilaterally is a _____ .
A purchase order
B scope of work description
C contract stipulation
D level of effort proposal
E request for proposal
參考答案:A
QUEST Fixed-price contracts place more risk on the _____ .
A owner
B contractor
C seller
D B and C
E All of the above.
參考答案:D
QUEST From an operating or functional perspective, there are various objectives of purchasing and materials management. Which is not one of these objectives?
A To buy competitively
B To support company operations with an uninterrupted flow of materials and services
C To develop reliable and effective sources of supply
D To achieve maximum integration with the other departments of the firm
E To attain approval from each department of every purchase
參考答案:E
QUEST _____ is a receipt issued by a carrier for merchandise to be delivered to a party at some destination.
A Proforma invoice
B Inspection certificate
C Packing list
D Bill of lading
E None of the above.
參考答案:D