QUEST Things that distort, distract, or muddle the communication process are called:
A noise
B selective filtering
C selective perception
D medium problems
E All of the above.
參考答案:A
QUEST Project managers must know:
A What kind of message to send
B to whom to send the message
C how to translate the message into a language that everyone can understand
D All of the above
E A and B only
參考答案:D
QUEST Communication management is best described as conducting or supervising
A the way we listen
B the way we speak
C the way we feel
D the exchange of information
E perfect documentation activities
參考答案:D
QUEST To determine whether or not the employee correctly understands the message, the project manager needs to:
A reduce the filtering
B eliminate barriers
C obtain feedback
D use more than one medium
E use all of the above.
參考答案:C
QUEST Surveys have shown that the primary skill needed to be a project manager is communication skill. The typical project manager spends approximately ______percent of his or her time communicating.
A 40-50
B 50-60
C 60-75
D 75-90
E 90-95
參考答案:D
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案一百零三
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)