2010年PMP美國項目管理考試習題及答案31
QUEST By which process may an unsuccessful supplier seek remedy for unjust awards?
A Contract dispute
B Stop work order
C Bid protest
D Coffective action
E None of the above.
參考答案:C
QUEST _____ is associated with a buyer's request for materials or equipment to meet a particular need or accomplish a specific purpose.
A Express warranty
B Implied warranty of merchantability
C Implied warranty of fitness for a particular purpose
D Prescribed warranty
E None of the above.
參考答案:C
QUEST There are four general classes of products that the purchasing department seeks to obtain for production. Which is not one of these categories:
A Raw materials
B Standard production items
C Special items
D Items of small value
E Semi-precious materials
參考答案:E
QUEST Which of the following types of specifications gives measurable capabilities of the product:
A functional specifications
B performance specifications
C conformance specifications
D technical specifications
E process capability specification
參考答案:B
QUEST Which of the following types of contracts allows the owner to transfer risk to the contractor:
A cost plus incentive fee
B cost sharing
C firm fixed price
D cost plus fixed fee
E performance guarantees
參考答案:C