QUEST Your client, with which you have good relations, wants you to provide him with office supplies. This task is not supported under your contract. You respond to your client's informal request using which medium?
A Speech
B Written
C Oral
D A and C
E Form letter
參考答案:C
QUEST As project manager, you wish to impose a standard method by which subordinates calculate project costs. Which level of communication should be required for this effort?
A Face-to-face
B Telephone
C Written
D Non-verbal
E All of the above should be required.
參考答案:C
QUEST You are in a meeting with someone who just ate a slice of garlic bread. Your are distracted by his pungent breath. Which of the following communication barriers describe these distractions?
A Sign Detection
B Sensory Limitations
C Selective Perception
D Varying Alertness of Perception
E None of the above
參考答案:A
QUEST How much time does the typical project manager spend communicating (formal and informal)?
A 40% - 60%
B 30% - 70%
C 60% - 80%
D 75% - 90%
E 25% - 55 %
參考答案:D
QUEST The standard types of communication include all but
A Written
B Verbal
C Telepathic
D Nonverbal
E None of the above
參考答案:C