1. In making key changes to a project, it is important to have a formal change process and a ____________ responsible for approving or rejecting requests.
Stakeholder
Change control board
Subject matter expert
Project manager
在項目做出重要變更時,重要的是要有一個正式的變更過程和一個負責批準或拒絕變更要求的 :
項目相關(guān)者
變更控制委員會
領(lǐng)域事務(wù)專家
項目經(jīng)理
2.In which project life cycle phase are the risks associated with project integration usually the smallest?
Project initiation and approval
Project planning
Project execution
Project closeout
在項目生命周期哪一階段,項目整合的風險最?。?
項目立項和審定
項目規(guī)劃
項目執(zhí)行
項目收尾
3.The most encompassing document to help the project team with project integration activities is the _________.
Project charter
Project plan
“As built” report
Scope change control procedure
能幫助項目團隊進行項目整合活動的最完整的文件是:
項目章程
項目計劃
進程報告
范圍變更控制流程
4. Prevention costs include all of the following, except:
Training
Supplier certification
Design reviews
Defect evaluation
預防成本包括所有下列事項,除了:
培訓
供應(yīng)商合格書
設(shè)計評審
缺陷評估
5. For the following group of numbers: 80, 10, 10, 50, 70 and 90, what is the standard deviation?
10
80
35
60
對于后面這組數(shù): 80,10,10,50,70 和 90,標準差是什么?
10
80
35
60
6. If a company wants to measure up to the Malcolm Baldrige National Quality Award, which of the following criteria will they be evaluated to?
ISO 9000
Quality policy
Strategic planning
ANSI standards
如果一家公司想要達到獲得Malcolm Baldrige國家質(zhì)量獎, 下列哪一標準將會是他們要進行評估的?
ISO 9000
質(zhì)量方針
戰(zhàn)略規(guī)劃
ANSI標準
7. When a process control chart is set up optimally, the upper and lower specification limits typically are:
Set equal to the upper and lower control limits
Set outside the upper and lower control limits
Set inside the upper and lower control limits
Set at two sigma from the mean value
當一個過程控制圖表被很理想建立完成時, 其規(guī)格要求的上限和下限通常是:
設(shè)定等于控制范圍的上限和下限
設(shè)在控制范圍的上限和下限之外
設(shè)在控制范圍的上限和下限之內(nèi)
設(shè)在均值的二個西格瑪sigma 水平
本站推薦
- 1PMP項目管理進度系統(tǒng),能否讓您的項目一馬當先?答案當然是肯定的!
- 2項目進度管理有難題?PMP系統(tǒng):一問就知,輕松解決
- 3PMP項目管理,項目進度管理的疑問終結(jié)者,您還在等什么?
- 4項目進度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
- 5PMP項目管理進度系統(tǒng),能否讓您的項目效率翻倍?答案就在這里!
- 6項目進度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
- 7項目管理不再迷茫,PMP進度系統(tǒng):您的疑問我來答
- 8PMP在手,項目進度管理難題還用問嗎?輕松搞定
- 9還在為項目進度頭疼?PMP管理系統(tǒng)幫您一問解千愁!