QUEST Many companies self insure against some risk. Problems which can arise from self-insurance include:
A failure to reserve funds to handle worst case scenarios (low probability events) resulting in severe financial damage to the company
B stiff competition from insurance companies
C confusion of business risks with insurable risks.
D A and C
E All of the above.
參考答案:D
QUEST Sensitivity analysis can be used in risk analysis to:
A Substitute for uncertainty analysis in risk quantification
B estimate the level of risk aversion adopted by management
C estimate the effect of change of one project variable on the overall project
D A and B
E All of the above.
參考答案:C
QUEST Risk event probability is defined as:
A the total number of possible events divided into the expectations or frequency of the risk event
B the number of times the risk event may occur
C the fraction of the total project tasks which may be affected by the risk event
D the total number of possible events divided into the consequences of the risk event.
E A and B
參考答案:A
QUEST In Project Risk Management, Risk Response may include actions to:
A reduce the probability of risk events
B change the scope, budget, schedule or quality specifications of the project
C reduce the consequences or severity of impacts of a potential risk event
D A and C
E All of the above.
參考答案:E
QUEST Total Project Risk:
A should not be calculated for small projects
B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D A and B
E A and C
參考答案:C
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案16
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)