QUEST Risk mitigation involves all but which of the following:
A developing system standards (policies, procedure, responsibility standards)
B obtaining insurance against loss
C identification of project risks
D performing contingent planning
E developing planning alternatives
參考答案:C
QUEST The principles of risk management should be followed only for:
A complex projects
B simple projects
C large projects
D A and C
E All of the above.
參考答案:E
QUEST The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .
A Is accomplished by paying the actual costs to the contractor.
B Is accomplished by paying the contractor for his costs plus a fixed fee (profit).
C Is an undisclosed contingency in the contractor's bid.
D Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.
E B and C
參考答案:C
QUEST Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?
A liability loss
B direct property loss
C profit loss
D personnel-related loss
E B and C
參考答案:C
QUEST Risk classified as unknown unknowns (i.e., those which cannot be identified or evaluated):
A should be deflected to the contracting officer
B should be handled via contingency allowances
C should be ignored, since they cannot be identified
D should be ignored, since they are not covered in the Project Risk Assessment
E C and D
參考答案:B