2010年P(guān)MP美國項目管理考試習(xí)題及答案19
QUEST Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?
A concept
B development
C execution
D conclusion
E All of the above.
參考答案:A
QUEST By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:
A Significantly reduce project risks
B eliminate project risks
C provide a rational basis for better decision making
D identify risks, their impact(s), and any appropriate responses
E None of the above.
參考答案:B
QUEST A contractor estimates that a project has a 0.5 probability of $200,000 profit and 0.3 probability of $50,000 loss. The expected monetary value of this project is:
A ¥200,000
B ¥150,000
C ¥85,000
D ¥50,000
E None of the above.
參考答案:C
QUEST Which of the following diagrams is most useful in impact analysis:
A arrow diagrams
B precedence diagrams
C decision trees
D Pareto diagrams
E cause and effects diagrams
參考答案:C
QUEST Which of the following risks are generally considered unpredictable:
A business risk
B financial risk
C inflation
D natural hazards
E taxes
參考答案:C