2010年P(guān)MP美國項目管理考試習題及答案八十三
QUEST Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .
A Project managers; team members
B Company management philosophy in treating employees; the average worker
C Project sponsors; project managers
D The functional team; project sponsors
E Recruitment policy; wage and salary administration
參考答案:B
QUEST In which organizational form do project managers usually get to know the employees well enough to provide an input into their performance review?
A Expediter
B Coordinator
C Pure project
D Matrix
E Line-staff
參考答案:C
QUEST In a matrix organizational form, MBO may be difficult to implement:
A If the functional employees are supervised closely by the line manager rather than the project manager
B Unless the project manager has an input into the employee's performance review
C Unless the project and line managers agree on the ultimate objective
D Unless the project and line managers agree to the duration of the task
E None of the above are correct answers
參考答案:E
QUEST Perhaps the biggest problem facing the project manager during integration activities within a matrix structure is:
A Coping with employees who report to multiple bosses
B Too much sponsorship involvement
C Unclear functional understanding of the technical requirements
D Escalating project costs
E All of the above
參考答案:A
QUEST The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form does the project manager probably have the easiest time in integrating work?
A Matrix
B Classical
C Expediter
D Coordinator
E Pure project
參考答案:E