2010年PMP美國項目管理考試習題及答案七十四
QUEST Most project management leadership theories focus on all of the following except:
A Personal characteristics of the project manager
B The situation at hand
C Personal traits of the subordinates
D Behavioral styles of the project manager
E Usefulness of authority and power in leadership
參考答案:C
QUEST Which theory(s) prescribes a form of participative management?
A theory X
B theory Y
C theory Z
D A or B
E B or C
參考答案:B
QUEST In which of the following organization(s) does the Functional Manager have the LEAST authority?
A coordinator
B weak matrix
C strong matrix
D functional
E expediter
參考答案:C
QUEST Project team building is most difficult in which type of environment?
A weak matrix organization
B strong matrix organization
C projectized organization
D functional organization
E expediter organization
參考答案:A
QUEST The core function of the PM is
A client interfacing
B project integration
C quality assurance
D personal administration
E All of the above.
參考答案:B