QUEST The auditing function that provides feedback about the quality of output is referred to as:
A quality control.
B quality planning.
C quality assurance.
D quality improvement
E All of the above.
參考答案:C
QUEST Cost of quality is:
A associated with non-conformance to specifications and requirements.
B primarily caused by poor workmanship of workers who are building or manufacturing the product.
C used to determine whether a quality management program is suitable for a given project.
D negligible for most large projects.
E A and B
參考答案:A
QUEST Quality management:
A is another name for careful inspections.
B is inversely related to productivity.
C is primarily the responsiblity of management.
D is primarily the responsibility of the workers.
E is essentially a motivational technique.
參考答案:C
QUEST Quality may be defined as:
A conformance to requirements.
B fitness for use.
C continuous improvement of products and services
D appeal to the customer
E All of the above except B
參考答案:E
QUEST Using the scenario in the special window, the project manager appears to be a _____ manager.
A 1, 9
B 9, 1
C 1, 1
D 9, 9
E 5, 5
參考答案:E
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案七十一
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)