2010年P(guān)MP美國項目管理考試習題及答案七
QUEST Using the WBS shown in the Special window, a typical work package would be:
A Software development
B Systems design
C Coding
D A, B, and C
E None of the above.
參考答案:E
QUEST Feasibility studies evaluate alternatives in terms of
A Cost-effectiveness
B Ease of performance
C Risk
D Safety
E All or part of A through D
參考答案:E
QUEST Project tradeoffs are usually made by comparing _____ and constraints.
A Time, cost, and quality
B Time, risk, and quality
C Risk, quality, and manpower availability
D Cost, quality, and technical performance
E Cost, quality, and risk
參考答案:D
QUEST The degree to which a company accepts and utilizes project management is often dependent upon the _____ and _____ of the project.
A Competition, dollar value
B Type of industry, manpower requirements
C Size, nature
D Quality requirements, manpower requirement
E Type of industry, risk
參考答案:C
QUEST Project management provides organizations with a methodology to:
A Become more efficient and effective in accomplishing goals that cannot be handled well by the traditional structure
B Manage high risk repetitive work
C Provide clients with multiple points of contact
D Provide guidance in accomplishing repetitive activities
E All of the above
參考答案:A
試題推薦:
2010年P(guān)MP美國項目管理考試習題及答案一
2010年P(guān)MP美國項目管理考試習題及答案二
2010年P(guān)MP美國項目管理考試習題及答案三
2010年P(guān)MP美國項目管理考試習題及答案四
2010年P(guān)MP美國項目管理考試習題及答案五
2010年P(guān)MP美國項目管理考試習題及答案六
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3