2010年P(guān)MP美國項目管理考試習(xí)題及答案九
QUEST A program can best be described as:
A A grouping of related activities which last two years or more
B The first major subdivision of a project
C A grouping of projects, similar in nature, which support a product or product line and have no definable end point
D A product line
E Another name for a project
參考答案:C
QUEST Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:
A The project manager
B The functional manager
C The project sponsor
D The client
E All of the above
參考答案:A
QUEST The project charter is a document designed to tell _____ exactly what the project entails.
A The project manager
B The project office
C The project team
D The project sponsor
E Anyone associated with the project
參考答案:E
QUEST Work authorization forms are needed in order to:
A Authorize line organizations to charge against the project
B Establish an audit trail
C Develop a structured methodology for release of funds
D All of the above
E A and C only
參考答案:D
QUEST The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
參考答案:E
試題推薦:
2010年P(guān)MP美國項目管理考試習(xí)題及答案一
2010年P(guān)MP美國項目管理考試習(xí)題及答案二
2010年P(guān)MP美國項目管理考試習(xí)題及答案三
2010年P(guān)MP美國項目管理考試習(xí)題及答案四
2010年P(guān)MP美國項目管理考試習(xí)題及答案五
2010年P(guān)MP美國項目管理考試習(xí)題及答案六
2010年P(guān)MP美國項目管理考試習(xí)題及答案七
2010年P(guān)MP美國項目管理考試習(xí)題及答案八
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選3