2010年P(guān)MP美國項目管理考試習(xí)題及答案25
QUEST The review for the specification completeness is performed during which of the following cycles.
A Award cycles
B requirements cycle
C requisition cycle
D solicitation cycle
E contractual cycle
參考答案:C
QUEST In which of the following is the cost of risk hidden by the contractor?
A Firm Fixed Price Contract
B Fixed Price Plus Incentive
C Cost Plus Fixed Price
D Cost Plus Percentage of Cost
E A and B
參考答案:D
QUEST The definitive terms of a contract are written during which of the following contract phases?
A Contract Phase
B Post-Award Phase
C Award Phase
D Pre-Award Phase
E Requirement Phase
參考答案:C
QUEST The _____ specification delineates specific end use capabilities which can be tested in the acceptance procedure.
A performance
B functional
C technical
D base line
E operational
參考答案:B
QUEST Which one of the following is not an acquisition method?
A advertising
B invitation
C negotiation
D purchase
E all are acquisition methods
參考答案:A