QUEST Which of the following is equivalent to a lump sum contract:
A fixed price contract
B price fixing contract
C purchase order
D All of the above.
E B and C only
參考答案:A
QUEST Which of the following terms is used to describe the receipt issued by a carrier for items to be delivered to a third party:
A free on board
B receipt for merchandise
C packaging list
D loading list
E bill of lading
參考答案:E
QUEST Which of the following is associated with a buyer's request for material to meet a particular need:
A material warranty
B material guarantees
C implied warranty of salability
D implied warranty of fitness for a particular purpose
E A and C only
參考答案:D
QUEST The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:
A post project evaluation
B post contract evaluation
C post mortem
D procurement performance evaluation
E contractor's performance evaluation
參考答案:E
QUEST Which of the following terms refers to the situation where the work is being used for the purpose intended and so certified:
A beneficial completion
B substantial completion
C project completion
D contract closeout
E final completion
參考答案:B
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案32
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
- 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
- 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
- 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
- 82010年一級建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級建造師執(zhí)業(yè)資格考試模擬試題(含答案)