2010年P(guān)MP美國項目管理考試習題及答案13
QUEST Range estimating in determining cost risk probabilities requires _____ .
A an amount of financial exposure.
B risks and opportunities ranked in order of bottom line importance
C contingency requirements for expected level of confidence
D probability of cost overrun occurrences
E All of the above.
參考答案:E
QUEST Standard deviation of project completion is _____ .
A a relationship of the uncertainty of critical path activities.
B an indicator of project end date target confidence
C a function of critical path, leveling and project costs.
D A and B
E All of the above.
參考答案:D
QUEST Which of the following does not contribute to increased Schedule Risk?
A labor shortage
B contractor claims
C lack of access
D sponsor scope changes
E all may increase schedule risk
參考答案:E
QUEST Screening of risk events for potential risk is known as _____ .
A problem structuring.
B risk identification
C risk quantification
D risk modeling
E risk mitigation
參考答案:B
QUEST The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.
參考答案:B