2010年P(guān)MP美國項目管理考試習題及答案七十六
QUEST The compromise conflict resolution technique
A is necessary when both participants must win.
B results in both sides losing
C is used when resolution is more important than relationships
D B and C
E All of the above.
參考答案:B
QUEST A life cycle project manager tends to have the following characteristics:
A balanced training
B stronger administrative skills than technical skills
C stronger technical skills than administrative skills
D stronger human resource skills
E None of the above.
參考答案:B
QUEST Which influence reflects an informal organization?
A formal authority
B reward power
C referent power
D expert power
E penalty
參考答案:C
QUEST The type of power most infrequently used by the PM is
A formal authority
B reward power
C referent power
D expert power
E penalty
參考答案:A
QUEST A key to successful Management by Objectives (MBO) is
A insuring that employees have clearly defined objectives
B involving employees in decision meetings
C permitting employees to set their own objectives
D allowing employees to perform their own evaluations
E A or C.
參考答案:E