QUEST A proven effective means to insure quality conformance is to:
A delegate accountability to subordinates
B revise quality specifications to match quality measurements
C train workers in proper quality methods
D inspect quality into the product
E make quality a higher priority than cost or schedule
參考答案:C
QUEST What is the relative priority of project Cost, Schedule and Quality?
A 1)Cost - 2)Schedule - 3)Quality
B 1)Quality - 2)Schedule - 3)Cost
C 1)Quality - 2)Cost - 3)Schedule
D 1)Schedule - 2)Quality - 3)Cost
E All are of equal priority
參考答案:E
QUEST The quality objectives are approved in the conceptual stage of the project by the:
A Project Engineer
B Project Manager
C Functional Manager
D Quality Assurance Manager
E Project Owner
參考答案:E
QUEST Of the following, who has the ultimate responsibility for meeting project quality objectives?
A Project Engineer
B Project Manager
C Functional Manager
D Quality Assurance Manager
E Project Owner
參考答案:B
QUEST Utility Theory:
A considers the risk propensity of the decision makers.
B is based on proven statistical methods.
C deals with the usefulness of the end product.
D is a key element of ISO 9000
E B and C
參考答案:A