QUEST The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A Time, schedule and cost.
B Management coordination and organization structuring.
C Work methods and accountability.
D Quality of work.
E Risk and impact decision-making.
參考答案:D
QUEST The scope baseline once established and approved, is used:
A as the basis for making future decisions.
B to accomplish verification measures.
C to evaluate potential changes.
D All of the above.
E A and C only.
參考答案:D
QUEST The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.
A Conceptual, charter/baseline.
B Conceptual, master schedule.
C Development, charter/baseline.
D Development, master schedule.
E Development, masterplan.
參考答案:A
QUEST Project management/project planning is most closely aligned with:
A Long range/strategic planning (5 years or more).
B Intermediate range planning (1 to 5 years)
C Short range/tactical planning (1 year or less).
D All of the above.
E B and C.
參考答案:E
QUEST Management decision-making includes:
A Analysis of alternatives.
B Revisions/replanning.
C Resource allocation.
D Modification or updating of goals and objectives.
E All of the above.