2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案三十四
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
QUEST A comparison of completion status to baseline is referred to as _____.
A Earned value measurement.
B Percent complete.
C ACWP.
D BCWS
E None of above.
參考答案:A
QUEST The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:
A Slack
B Free float.
C Restricted float.
D Level float.
E Lag
參考答案:E
QUEST Overlapping activities on a project, such as design and construction, is referred to as:
A Fast tracking
B Risk conversion.
C Parallel management.
D Process improvement.
E Synchronous manufacturing
參考答案:A
QUEST A computer tape which contains historical project information is called ____ tape.
A Database
B Baseline.
C Archive.
D Lessons learned.
E Life cycle summary.
參考答案:C
QUEST Which method shown below is acceptable for reducing cost or shortening the schedule?
A "Crashing"
B Changing scope.
C Performing activities in parallel rather than in series.
D All of the above.
E A and C only.
參考答案:D
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案三十三
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)