QUEST Good project objectives must be:
A General rather than specific
B Established without considering resource bounds
C Realistic and attainable
D Overly complex
E Measurable, intangible and verifiable
參考答案:C
QUEST Researching, organizing and recording pertinent information is called:
A Alternative analysis
B Information gathering
C Configuration management
D Post project analysis
E All of the above
參考答案:B
QUEST The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
參考答案:A
QUEST The sequential steps that define the process for successfully completing a project is:
A Implementation Plan
B a life cycle
C Development Plan
D a critical path
E Management Plan
參考答案:B
QUEST What is the purpose of the Project Plan?
A To document the Preliminary estimates.
B To document the Definitive estimates.
C To document the Budgetary estimates.
D To document Parametric estimates.
E To document Order of Magnitude estimates.
參考答案:C