2010年P(guān)MP美國項目管理考試習(xí)題及答案五
QUEST Which of the following can be tracked using the WBS?
A time
B cost
C performance
D scope
E None of the above.
參考答案:D
QUEST Which of the following are types of status reports?
A document, variance, trend and exception
B cost, trend, schedule and acquisition
C cost, schedule, technical performance
D analysis, cost, performance and schedule
E All of the above.
參考答案:C
QUEST You have been assigned as a project leader and must first review the statement of work provided by the customer. Which of the following is most often overlooked?
A Data item deliverables
B Customer-furnished equipment and facilities
C Long-lead procurement items
D Customer-imposed milestones
E Other subcontractor interface requirements
參考答案:A
QUEST During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform a given task. The best way for the project manager to handle this would be to:
A Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.
B Let the affected line groups decide among themselves who will perform the work
C Ask the executive sponsor to make the decision
D Allow each line group to perform part of the task
E All of the above
參考答案:B
QUEST The most common definition of project success is:
A Within time
B Within time and cost
C Within time, cost and technical performance requirements
D Within time, cost, performance and accepted by the customer/user
E None of the above
參考答案:D
試題推薦:
2010年P(guān)MP美國項目管理考試習(xí)題及答案一
2010年P(guān)MP美國項目管理考試習(xí)題及答案二
2010年P(guān)MP美國項目管理考試習(xí)題及答案三
2010年P(guān)MP美國項目管理考試習(xí)題及答案四
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選3