成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓
當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
2010年P(guān)MP美國項目管理考試習題及答案八十二
QUEST In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?
A Not working directly with the assigned functional employees
B Employees spend only a short amount of time assigned to the project
C Not being knowledgeable enough to evaluate employees on technical judgment
D All of the above
E A and B only
參考答案:D
QUEST The behavioral responsibilities of a project manager may also include dealing with:
A The public
B Regulatory personnel
C The legal environment
D Environmental issues
E All of the above
參考答案:E
QUEST Which of the following fall(s) under the responsibilities of a project manager?
A Labor relations with project personnel
B Affirmative action
C Personnel training
D Discrimination and equal employment opportunity
E All of the above
參考答案:E
QUEST Team members want to work for a project manager that can provide them with career path planning. In which organizational form is career path planning difficult for project employees?
A Matrix
B Pure project
C Project coordinator
D Project expediter
E Classical/traditional
參考答案:B
QUEST The Delphi Method is well-suited for:
A Decision-making
B Forecasting
C Overhead rate estimating
D All of the above
E A and B only
參考答案:E
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習題及答案八十一
試題推薦:
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3