2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案六十九
申請(qǐng)免費(fèi)試用、咨詢(xún)電話:400-8352-114
QUEST Which of the following statements about the cost of quality are true?
A the cost of quality is the expense of nonconformance to requirements and specifications.
B the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.
C quality control programs should be implemented when the cost of quality are deemed affordable by management.
D A and B.
E A and C
參考答案:A
QUEST Japanese quality control has improved dramatically in the last 30 years for all of the following reasons except:
A the use of quality circles.
B small, continuous improvements in quality control.
C the use of worker suggestion systems.
D the use of quality control charts.
E focusing quality control efforts on production outputs.
參考答案:E
QUEST Control chart theory is based on the differentiation of the causes of variations in quality. Variations may be produced by assignable causes. All of the following are examples of assignable causes except:
A differences among machines.
B differences among workers.
C differences among materials.
D differences in each of these factors over time.
E None of the above (all are examples)
參考答案:E
QUEST The rule of seven used by quality control engineers states that if a run of seven or more samples lays on one side of the process mean, then the process is out of control. What is the probability that this condition is the result of random variations.
A 14.30%
B 3.12%
C 2.73%
D 1.56%
E 0.78%
參考答案:D
QUEST Two sources of variation in the length of hex bolts exist. Production variation and measurement error. The QC manager knows that the standard deviation from these sources is 0.24" and 0.43" , respectively. What is the total standard deviation.
A .10 inch.
B .19 inch.
C .34 inch.
D .49 inch.
E .67 inch.
參考答案:D
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案六十八
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)