QUEST Which of the following is referred to as payback period:
A the number of periods required to recover the initial investment
B the rate of return on the investment
C the number of periods required to bring project cost back to the original budget, based on current performance
D loan payment schedule
E None of the above
參考答案:A
QUEST Which of the following is referred to as sunk cost:
A management reserve
B contingency fund
C cost budgeted for construction under water
D expended funds over which there is no further control
E forecasted budget over-runs
參考答案:D
QUEST The future value of an annual income flow of $1000 for 2 years at 10% is:
A ¥2,200
B ¥2,280
C ¥2,300
D ¥2,310
E None of the above
參考答案:D
QUEST The net present value of $110 one year from now at 10% is:
A ¥100
B ¥120
C ¥121
D $100 less taxes
E $100 less taxes and interest
參考答案:A
QUEST Which of the following depreciation methods provides for accelerated depreciation of an asset:
A Double declining balance.
B Straight line.
C Exponential depreciation
D Double sum of the years digits
E Double increasing balance
參考答案:A
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案四十五
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)