2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案三十六
QUEST In the PDM, common constraints include:
A Start-to-start
B Finish-to-start
C Finish-to-finish
D B and C only
E A, B, and C.
參考答案:E
QUEST Activities with zero time duration are referred to as:
A Critical path activites.
B Noncritical path activities.
C Slack time activities.
D Dummies
E None of above.
參考答案:D
QUEST In the arrow diagramming method (ADM), _____ do not consume time or resources.
A Events.
B Activities
C Slack elements.
D B and C only.
E All of the above.
參考答案:A
QUEST On a precedence diagram, the arrow between two boxes is called:
A An activity.
B A constraint.
C An event.
D The critical path.
E None of above.
參考答案:B
QUEST A project element which lies between two events is called:
A An activity.
B A critical path method.
C A slack milestone.
D A timing slot.
E A calendar completion point.
參考答案:A
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案三十五
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
- 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
- 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
- 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
- 82010年一級建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級建造師執(zhí)業(yè)資格考試模擬試題(含答案)