成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓
當(dāng)前位置:工程項(xiàng)目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項(xiàng)目管理工具
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案二十八
QUEST On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:
A ¥-100
B ¥100
C ¥-150
D ¥150
E 85%
參考答案:C
QUEST A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:
A 1.50%
B 33.00%
C 75%
D 67%
E None of the above.
參考答案:B
QUEST Resource leveling will often affect the project by making it:
A Shorter.
B Longer
C More responsive to customer needs.
D A and C
E B and C.
參考答案:B
QUEST Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A 2
B 3
C 4
D 5
E 7
參考答案:C
QUEST Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.
A 2, 10
B 4, 12
C 6, 14
D 7, 15
E 9, 17
參考答案:A
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案二十七
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
- 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
- 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
- 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
- 82010年一級建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級建造師執(zhí)業(yè)資格考試模擬試題(含答案)