2010年PMP美國項目管理考試習題及答案二十四
QUEST The most frequently used construct in Precedent Diagramming Method is:
A Start to Start.
B Finish to Finish.
C Start to Finish.
D Finish to Start.
E Dummy activity.
參考答案:D
QUEST The critical path is calculated by
A subtracting the end date of task one from the start date of task two.
B determining which tasks have the least amount of total slack.
C totaling the time for all activities.
D determining the shortest path through the network.
E Determining which tasks have the most slack
參考答案:B
QUEST Using the table in the Special window, Which task is completed?
A dig hole
B remove debris
C survey
D set forms
E place concrete
參考答案:B
QUEST Which may be employed to shorten a schedule without changing the scope of the task?
A Fast tracking.
B Crashing
C Releasing resources earlier from tasks which were scheduled with a late start.
D Alter to task priorities.
E A or B
參考答案:A
QUEST Resource leveling _____.
A Allocates resources to activities to find shortest schedule within fixed resource limits.
B Smoothes out resource requirements by rescheduling activities within their float time.
C Smooths out resource requirements by substituting activities with unassigned resources.
D Attempts to reduce resource requirements within a constraint on project duration
E B or D
參考答案:E