QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ .
A Project specification tree.
B Customer's deliverable list.
C Customer's milestone dates.
D Work breakdown structure.
E Listing of customer team meeting dates.
參考答案:D
QUEST The critical path in a network is the path that:
A Has the greatest degree of risk.
B Will elongate the project if the activities on this path take longer than anticipated.
C Must be completed before all other paths.
D All of the above.
E A and B only.
參考答案:B
QUEST The major difference between PERT and CPM networks is:
A PERT requires three time estimates whereas CPM requires one time estimate.
B PERT is used for construction projects whereas CPM is used for R & D.
C PERT addresses only time whereas CPM also includes cost and resource availability.
D PERT requires computer solutions whereas CPM is a manual technique.
E PERT is measured in days whereas CPM uses weeks or months.
參考答案:A
QUEST A calendar that identifies when a project may be performed on an activity is called a:
A Project calendar.
B Resource calendar.
C Milestone point.
D Key point.
E Work unit.
參考答案:A
QUEST Planning activities such that predetermined resource availability pools are not exceeded is called:
A Resource leveling.
B Manpower leveling.
C Resource limited planning.
D Manpower planning.
E Manpower contingency planning.
參考答案:C
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案三十二
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)