QUEST Work packages are used to:
A Represent units of work at a level where work is performed.
B Clearly distinguish one work package from all others assigned to a single functional group.
C Limit the work to be performed to relatively short periods of time.
D All of the above.
E A and B only
參考答案:D
QUEST Project life cycles are very useful for _____ and _____ .
A Configuration management, termination
B Objective setting, information gathering
C Standardization, control
D Configuration management, weekly status updates
E Approval, termination
參考答案:C
QUEST Which of the following are included as part of a scope statement?
A Project justification
B Project deliverables
C Project objectives
D All of the above
E B and C
參考答案:D
QUEST The initial document that formally recognizes the existence of a project is the _____ .
A Scope baseline
B Management plan
C Project charter
D Configuration control report
E None of the above
參考答案:C
QUEST Which of the following is not a scope management process?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
參考答案:D
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)