2010年PMP美國項目管理考試習題及答案四十四
QUEST Using the situation stated in the Special window, what is the total variable costs for producing one widget?
A ¥1,020
B ¥1,010
C ¥1,015
D ¥20
E None of the above.
參考答案:E
QUEST A technique that can be used to measure the total income of a project compared to the total moneys expended at any period of time is:
A return on investment (ROI)
B net present value (NPV)
C discounted cash flow (DCF)
D B and C
E All of the above.
參考答案:E
QUEST Cost management includes processes that are required to maintain financial control of projects. These processes may include:
A economic evaluation
B cost estimating
C cost forecasting
D B and C
E All of the above.
參考答案:E
QUEST Which of the following is considered a method of accelerated depreciation:
A sum-of-the-years digit
B straight-line
C double-declining-balance
D A and C
E All of the above.
參考答案:D
QUEST The Cost Performance Index is computed as:
A budget cost of work performed divided by actual cost of work performed
B budget cost of work performed minus actual cost of work performed
C budget cost of work performed minus budget cost of work scheduled
D budget cost of work scheduled divided by budget cost of work performed
E actual cost of work scheduled divided by budget cost of work performed
參考答案:A