2010年P(guān)MP美國項目管理考試習(xí)題及答案四十二
QUEST Using the situation stated in the Special window, what is the cost performance index for Case #9?
A 1.1
B 1.91
C 0.83
D 1.2
E None of the above
參考答案:A
QUEST Sunk costs are:
A future costs held in reserve.
B costs invested in commodities.
C expended costs over which we have no control.
D expended costs over which we have no more control
E tax credits
參考答案:D
QUEST Managerial Reserves are:
A allowances to account for price changes that can occur over the life of a project.
B incentive fees paid to managers for good performance.
C funds used to offset poor cost or schedule estimates.
D accounts to allocate and maintain funds for contingency programs
E All of the above.
參考答案:D
QUEST Life Cycle Costing:
A is the concept of including all costs within the total life of a project.
B is an activity devoted to optimizing cost/performance
C is an activity of appraising the cost and technical performance of a completed project.
D is a process of predicting the life of a project.
E None of the above.
參考答案:A
QUEST Using the situation stated in the Special window, what is the schedule variance for Case #8?
A 1000
B 2000
C -1000
D -2000
E 0
參考答案:C