2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案五十二
QUEST An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:
A Higher salaried employees were assigned.
B Overtime was required.
C The overhead rate increased.
D Employee salaries had increased.
E Any of the above
參考答案:E
QUEST During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:
A The project will be completed late.
B The critical path has been lengthened.
C the costs are being overrun.
D Overtime will be required to maintain the original critical path.
E None of the above.
參考答案:E
QUEST Using the situation stated in the Special window, the total price variance of direct material is:
A ¥80,245
B ¥-4,236
C ¥-3,479
D ¥1
E ¥83,994.00
參考答案:C
QUEST Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A Become worse, become worse
B Become worse, improved
C Improved, increased
D Improved, become worse
E None of the above are correct
參考答案:E
QUEST A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.
A Trend line.
B Trend analysis.
C S curve.
D Percent completion report.
E Earned value report.
參考答案:C
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案五十一
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
- 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
- 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
- 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
- 82010年一級建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級建造師執(zhí)業(yè)資格考試模擬試題(含答案)