QUEST Cost forecasting calculations include:
A EAC = ACWP + (BAC - BCWP)
B EAC = BAC/CPI
C EAC = ACWP + (BAC/CPI)
D All of the above.
E A and B
參考答案:E
QUEST The Cost Performance Index (CPI) measures
A total costs
B performance over a period of time
C costs at a point of time
D variable costs
E All of the above.
參考答案:C
QUEST Parametric cost estimating involves
A using the WBS to do bottom up estimates
B defining the perimeters of the life-cycle
C calculating the individual estimates of work packages
D using a statistical model to estimate costs
E A and C
參考答案:D
QUEST Which of the statements regarding benefit-cost analysis in the Special window are true?
A 1 and 2
B 2 and 3
C 1 and 3
D 1, 2 and 3
E None of the above.
參考答案:C
QUEST Present value measures
A the value to us today of future cash flows.
B the rate of return on an investment when we take account of cash inflows and outflows
C the current estimates of our project budget
D the dollars worth of work accomplished as of today
E All of the above.
參考答案:A
相關(guān)試題:
2010年P(guān)MP美國(guó)項(xiàng)目管理考試習(xí)題及答案四十
試題推薦:
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國(guó)項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測(cè)
- 4交通部試驗(yàn)檢測(cè)師:交通安全設(shè)施測(cè)試題(2010年度)
- 5交通部試驗(yàn)檢測(cè)工程師:橋涵工程試驗(yàn)檢測(cè)試題(2010年度)
- 62010年公路工程試驗(yàn)檢測(cè)師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測(cè)師:公路、材料測(cè)試題(2010年度)
- 82010年一級(jí)建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國(guó)一級(jí)建造師執(zhí)業(yè)資格考試模擬試題(含答案)