2010年P(guān)MP美國項目管理考試習題及答案四十
QUEST Value engineering/Analysis is the systematic use of techniques which does not include _____.
A establishing values for required functions
B provide the required functions at the lowest overall cost.
C identifies the required function of an item
D seeks to trade performance for cost
E None of the above.
參考答案:D
QUEST The ability to achieve cost savings is inversely proportional to _____.
A the earned value achieved to date
B the estimated costs to complete
C empowerment to the P.M.
D productivity
E None of the above.
參考答案:A
QUEST The estimated cost to complete (ETC) is _____.
A BCWP/ACWP
B the forecasted and final cost - cost to date
C (ACWP-BCWP)/BCWP * 100
D Total estimate - ACWP
E None of the above.
參考答案:B
QUEST Considering alternate suppliers is a form of _____.
A Value engineering.
B Risk Analysis
C Contract Management
D Project integration
E All of the above.
參考答案:A
QUEST You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:
A The project is operating at a favorable cost efficiency ratio.
B the project is spending more than planned
C the project is behind schedule
D the project is ahead of schedule
E B and C
參考答案:C